Compound to be set up on public grassland in Milton Keynes for work to remove cladding from apartment complex

Combustible cladding at a Milton Keynes apartment complex is to be replaced under a scheme proposing a construction compound on public grassland for around three years.

Barratt Redrow has submitted a planning application, through agent Lawtech Group, to install the temporary compound off South Row to support fire remediation works at Vizion Apartments.

The compound application is under consultation with Milton Keynes City Council, with no decision recorded on the planning register.

A planning statement says the development comprises 12 buildings, nine of which are classified as Higher-Risk Buildings. The remaining three are below 18 metres.

A view of the land in Central Milton Keynes on which the compound is set to be installed. Image courtesy of Google Street View.placeholder image
A view of the land in Central Milton Keynes on which the compound is set to be installed. Image courtesy of Google Street View.

The contractor says the scheme will replace combustible materials with non-combustible alternatives to ensure the blocks are safe and comply with regulations.

The work involves the cladding façade finishes and their supporting rail structure, according to the document.

Lawtech says it received instructions from Barratt Redrow, acting as employer’s agent on behalf of client Avon Ground Rents Limited, to undertake the cladding replacement and remediation.

The application concerns the temporary site set-up and compound needed to support that work.

Public grassland between South Row and H6 Childs Way would be used for site welfare facilities and materials storage for approximately three years.

The area would be enclosed by a 2.4-metre-high timber hoarding, with lockable gates for vehicles and pedestrians. Pedestrian lighting would be installed on the hoarding.

Parking bays at the entrance would be suspended for the duration of the compound’s use, although the statement does not specify how many spaces would be affected.

A banksman would control all vehicle movements. Temporary fences and barriers would separate pedestrians from working areas and routes wherever possible, with designated pedestrian routes provided.

Lawtech says it is entering into a licence agreement to rent the grassland for the works.

The statement says small trees stand within the proposed compound area and that the Parks Trust has agreed to remove them before the contractor takes possession.

It says trees will be replanted after the works and the land restored to its original condition.

The grassed area would be lowered to accommodate a stone base topped with tarmac, providing a clean surface intended to prevent dirt and debris spreading onto surrounding block-paved parking areas.

Hoarding would be positioned outside tree canopies to protect roots, while geogrid membranes would spread vehicle loads at the entrance where required by the Parks Trust.

The document says the proposal would not change the residential use of the surrounding buildings.

Lawtech’s statement identified August 2026, or as soon as practicably possible, as the intended date for setting up the site. It does not confirm whether the compound has since been established.

Have you got a story you want to share with our readers? You can now send it to us online via YourWorld at https://www.yourworld.net/submit/ It's free to use and, once checked, your story will appear on our website and, space allowing, in our newspapers.

Related topics:
News you can trust since 1981
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice